News

Go back to news listing

Street Improvement Program Construction Begins

Posted on Aug. 17 2022
Aerial view of Spruce Drive. Click to image enlarge.
Aerial view of Spruce Drive. Click to image enlarge.

The annual street improvement plan (SIP) is underway in the Drumheller Valley, including a large project on Spruce Drive. The work is being completed by Brooks Asphalt & Aggregate Ltd., which was awarded the SIP tender earlier this year.

Spruce Drive is divided into Area A and Area B. Area B will see a complete road reconstruction, while Area A will see a Mill & Overlay.

Spruce Drive

  1. Full Road Closure (12 Spruce Drive - 914 11 St SE), August 24 - September 9, reopening for the long weekend then closing again starting September 2
  2. Road Coring (Area B), September 24 - 27
  3. Area B Base Prep and First Lift of Asphalt, August 29 - 30
  4. Area A Milling, September 6
  5. Area A & B Paving, September 6 - 9
  6. Miscellaneous Concrete Repairs (sidewalks, curbs and gutters), August 16 - 28

Remaining Concrete Repairs

  • August 17, approximately 4 - 5 weeks

CN Rails to Trails

  • August 29, approximately 3 - 4 weeks

Questions or concerns regarding the construction process can be forwarded to Troy Smith of Brooks Asphalt & Aggregate at 403-633-7894.

Supporting documentation

The Approved 2022 Street Improvement Program Scaled Back due to Inflationary Costs

Streets & Bridges tender category

Prev Next

Recent News

I Want To